Hi all,
The teams are are working on the external aspect of the tank and are progressing well today. We are currently laying strips of bonded membrane to the expansion joints which allow the concrete structure to move without cracking the concrete. We are almost half way there!
We are also working on some narrow gullies which are used to dispalce the water from the roof and they are very narrow, making access tricky. We are focusing on particular areas to avoid an issues and are currently still on schedule.
The repairs to the concrete are complete and all of the works are at a great standard of work.
Thank you for your patience and we will update you again soon. If you have any questions, please post below.
Ben
.